Project Title

:

One House One Farm

(Ektee Bari Ektee Khamar)

Sponsoring Ministry/Division

:

Rural Development and Cooperative Division, Ministry of Local Government, Rural Development & Cooperatives

Executing Agency

:

Rural Development and Cooperative Division, Ministry of Local Government, Rural Development and Cooperatives with District Administration in particular Deputy Commissioner and his officials. Bangladesh Rural Development Board (BRDB) as the main support agency along with other departments like Co-operatives, Bangladesh Academy for Rural Development (BARD), Comilla, PDBF, SFDF and Rural Development Academy (RDA), Bogra.

Project Implementation Period

:

Original: July 2009-June 2014

Revised: July 2009-June 2016

Cost of the project (Taka in Crore)

:

Original:1197.00

Revised: 3163.00

Location of the project (Revised DPP)

:

Division

District

Upazila

Union

Village

7

64

485

4503

40527

Cumulative Progress up to September, 2013

 

Description

Target Plan

Achievements Comments

1

2

3 4

Selection of Union

4503

4503

Selection of Beneficiaries

24,31,620

24,00,000

Village Organization

40,527

40,000

Saving (Taka in Crore)

1077.00

355.00

Bonus
(Taka in Crore)

1077.00

355.00

Post Training Support Fund (PTS)
(Taka in Crore)

1241.00


490.00

Asset Transfer

Milch Cow

90,000

47,800

GI Sheet Tin (Bandle)

1,93,280

41,980

Poultry Birds (Family)

96,400

10,600

Seeds of vegetable (Family)

2,89,164

55,980

Tree Plantation (Family)

96,400

38,300

Expenditure of the Project

Financial Year

Allocation

Expenditure (Taka in Lakh)

(Taka in Lakh)

Revenue

Capital

Total

1

2

3

4

5

2009-2010

800.00

172.75

546.46

719.21

2010-2011


26936.00


14427.31


3986.04


18413.35


2011-2012

44210.75


42784.97

1248.18

44033.16

2012-2013

53800.00


51366.50

292.81

51659.31